Hammersmith Hospital

Hammersmith Hospital

May 2018


This was a large project which we carried out on behalf of GDP, for the NHS trust at Hammersmith Hospital, Du Cane Road London.

Task:
To Plane off whole car park area.
Excavate existing kerb line (vehicles were causing a problem over hanging the foot way and blocking pedestrian access, this was causing problems as there are a lot of wheel chair users in this area).
Installation of new kerb line to widen footway.
Resurface by mechanical paving machine to car park area using Stone Mastic Asphalt.
To resurface footway using 6mm dense binder macadam.
To re line parking bays to new design to stop vehicles over hanging the footway.
To refurbish and carry out small repairs to existing crash barrier.
Project approximately 4 weeks.