Marlborough Town

Marlborough Town

January 2018


Carris will -
• Overlay more than 100 metres of .1CU HV Underground Cable with 150 XPLE from High Street S/S and breech joint teeing into The Green S/S and Waggon Yard S/S.
• Lay almost 400 metres of 150 XPLE Cable along Coldharbour Lane ringing into new RMU at Coldharbour Lane S/S.
• Close existing open points and establish 2 x new open points.
• Carry out all jointing as required.
• Carry out reinstatement and making good of any areas excavated or where work has occurred.